Bridge not built on Son river in 6 years: A day ago in Anuppur, a boat full of school children overturned, the administration talked about building a bridge by 2023

More articles

Saurabh Guptahttp://karekaise.in
Get information about Stock Market and Crypto currency follow us or click on our website link - https://karekaise.in/

A boat full of students who came to study government Umavi Chachai from Bakeli in Anuppur district overturned on Thursday while crossing the Son river. No student was seriously injured during the boat capsizing. The collector instructed the villagers not to cross the Chachai Son river. Boat operation is prohibited. It is being told that the amount was approved in 2016 for the construction of a bridge on this river, but till date the bridge has not been built.

Bridge not built on Son river in 6 years: A day ago in Anuppur, a boat full of school children overturned, the administration talked about building a bridge by 2023

Collector started bus facility


The Collector has issued instructions to the Public Works Department to immediately barricade and home guards to keep a vigil at the said site. Eklavya Model Residential U.M.V. under Tribal Affairs Department on the instructions of Collector Sonia Meena for students going from Bakeli to Chachai. Anuppur bus facility is provided. So that the studies of the students are not affected.

The bus will reach Bakeli at 9:15 am to take the school students from Bakeli to school. Departing from Kakrehli Tola Community Sanitation Complex in Bakeli at 9.30 am, Sandha will reach Chachai Vidyalaya via Anuppur and after school timings the bus will reach back to Bakeli with the students.

The construction of this bridge was to be completed on 8th September 2019, but in the meantime the water level at the bridge construction site increased due to the construction of a pucca dam by Orient Paper Mill, Amlai. This made foundation work impossible. He said that in the month of April 2022, the work has been taken forward when the water level is low. Work on two slabs of the bridge is pending.

The administration is claiming to complete this bridge by 2023, but it remains to be seen how much truth is there in it. He said that the delay in the work has also happened due to the corona epidemic, but the bridge construction work will be completed soon as soon as the rains subside. The surprising thing is that since 2019, the administration is waiting for the water to recede in the Son river.

541.02 lakh is issued for the bridge 


Let us inform that on December 14, 2016, Rs 541.02 lakh was approved for the construction of a bridge on the Son river located on the Baba Kuti (Chachai) to Bakeli road. M/s Amphah Infrastructure Pvt. Ltd. was given to New Delhi. The contracted cost of the work was 518.90 lakhs.